Daviot Windfarm BEGA
Cubico UK Development Limited at INVERNESS 132/33KV GRID SUPPLY POINT SUBSTATION
- Connection date
- 31 Oct 2030
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Onshore wind
- Total capacity
- 45 MW
- Connected now
- 0 MW
- Still to connect
- 45 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-004874
- In the register since
- January 2024
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 30 Jun 2026 registerConnection point changed from Inverness GSP to INVERNESS 132/33KV GRID SUPPLY POINT SUBSTATION
- 30 Jun 2026 registerMarked as Gate 1
- 27 Jun 2025 registerRenamed from Daviot Windfarm
- 27 Jun 2025 registerConnection point changed from Daviot 132/33kV Substation to Inverness GSP
- 27 Jun 2025 registerConnection date moved from 31 Mar 2031 to 31 Oct 2030 (−5 months)
- 27 Jun 2025 registerAgreement type changed from Direct Connection to Embedded
- 27 Sep 2024 registerConnection point changed from Inverness GSP to Daviot 132/33kV Substation
- 26 Apr 2024 registerCustomer changed from PEEL CUBICO RENEWABLES LIMITED to CUBICO UK DEVELOPMENT LIMITED
- 30 Jan 2024 registerAdded to the register
Also at INVERNESS 132/33KV GRID SUPPLY POINT SUBSTATION
Substation viewNo other projects in the register at this connection point.