Old Stoke Rd BESS
Cubico UK Development Limited at North Anglia Connection Node A 132kV Substation
- Connection date
- 31 Oct 2034
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 105 MW
- Connected now
- 0 MW
- Still to connect
- 105 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-005896
- In the register since
- June 2025
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 13 Nov 2026 registerMarked as Gate 1
- 27 Jun 2025 registerAdded to the register
Also at North Anglia Connection Node A 132kV Substation
Substation view3 other projects, 813 MW still to connect at this substation in total.