- Connection date
- 31 Oct 2037
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 300 MW
- Connected now
- 0 MW
- Still to connect
- 300 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-006059
- In the register since
- June 2025
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 1 May 2026 registerMarked as Gate 1
- 27 Jun 2025 registerAdded to the register
Also at North Anglia Connection Node A 400kV
Substation view5 other projects, 2.9 GW still to connect at this substation in total. 2.6 GW is due to connect here before this project’s connection date of 31 Oct 2037.
- Norwich Main BESSTASWAY ENERGY PARK LIMITED, Storage with solar or wind, Gate 1Oct 2032950 MW
- GF Norwich BESSGF Norwich Energy Ltd, Storage, Gate 1Oct 2034400 MW
- Long Stratton 400ENSO GREEN HOLDINGS X LIMITED, Storage with solar or wind, Gate 1Oct 2034400 MW
- Long Stratton BESSField Long Stratton Ltd, Storage, Gate 1Oct 2034400 MW
- Noventum -Long StrattonNoventum Power Solar 8 Limited, Storage with solar or wind, Gate 1Oct 2034460 MW