548 UK INVESTMENT HOLDINGS LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Patford Bridge Farm | Patford Bridge 400kV Substation | Storage with solar or wind | 200 | 31 Oct 2033 | Gate 1 | Scoping |
Left the register since January 2021: Bulls Lodge Farm (200 MW), Bulls Lodge Farm 2 (350 MW), Enderby Farm (200 MW), Enderby Farm 2 (700 MW), Marston Farm 2 (350 MW), Patford Bridge Farm 2 (350 MW), Ryhall Farm (200 MW), Sundon Farm (200 MW), Sundon Farm 2 (700 MW), Yaxley Farm (200 MW), Pelham Farm 2 (700 MW), Pelham Farm (700 MW).
Recent changes
- Bulls Lodge FarmEngland and Wales, Storage with solar or windLeft the register (200 MW from 30 Apr 2033)200 MW
- Bulls Lodge Farm 2England and Wales, Storage with solar or windLeft the register (350 MW from 30 Mar 2033)350 MW
- Enderby FarmEngland and Wales, Storage with solar or windLeft the register (200 MW from 31 Oct 2034)200 MW
- Enderby Farm 2England and Wales, Storage with solar or windLeft the register (700 MW from 31 Oct 2034)700 MW
- Marston Farm 2England and Wales, Storage with solar or windLeft the register (350 MW from 31 Oct 2032)350 MW
- Patford Bridge Farm 2England and Wales, Storage with solar or windLeft the register (350 MW from 31 Oct 2033)350 MW
- Ryhall FarmEngland and Wales, Storage with solar or windLeft the register (200 MW from 31 Oct 2034)200 MW
- Sundon FarmEngland and Wales, Storage with solar or windLeft the register (200 MW from 29 Oct 2032)200 MW
- Sundon Farm 2England and Wales, Storage with solar or windLeft the register (700 MW from 29 Oct 2032)700 MW
- Yaxley FarmEngland and Wales, Storage with solar or windLeft the register (200 MW from 31 Oct 2032)200 MW
- Pelham Farm 2England and Wales, Storage with solar or windLeft the register (700 MW from 31 Oct 2032)700 MW
- Pelham Farm 2England and Wales, Storage with solar or windListed again
- Bulls Lodge FarmEngland and Wales, Storage with solar or windListed again
- Bulls Lodge Farm 2England and Wales, Storage with solar or windListed again
- Enderby FarmEngland and Wales, Storage with solar or windListed again
- Enderby Farm 2England and Wales, Storage with solar or windListed again
- Marston Farm 2England and Wales, Storage with solar or windListed again
- Patford Bridge FarmEngland and Wales, Storage with solar or windListed again
- Patford Bridge Farm 2England and Wales, Storage with solar or windListed again
- Ryhall FarmEngland and Wales, Storage with solar or windListed again
- Sundon FarmEngland and Wales, Storage with solar or windListed again
- Sundon Farm 2England and Wales, Storage with solar or windListed again
- Yaxley FarmEngland and Wales, Storage with solar or windListed again
- Bulls Lodge FarmEngland and Wales, Storage with solar or windNot in this register
- Bulls Lodge Farm 2England and Wales, Storage with solar or windNot in this register
- Enderby FarmEngland and Wales, Storage with solar or windNot in this register
- Enderby Farm 2England and Wales, Storage with solar or windNot in this register
- Marston Farm 2England and Wales, Storage with solar or windNot in this register
- Patford Bridge FarmEngland and Wales, Storage with solar or windNot in this register
- Patford Bridge Farm 2England and Wales, Storage with solar or windNot in this register
- Ryhall FarmEngland and Wales, Storage with solar or windNot in this register
- Sundon FarmEngland and Wales, Storage with solar or windNot in this register
- Sundon Farm 2England and Wales, Storage with solar or windNot in this register
- Yaxley FarmEngland and Wales, Storage with solar or windNot in this register
- Pelham Farm 2England and Wales, Storage with solar or windNot in this register
- Patford Bridge FarmEngland and Wales, Storage with solar or windMarked as Gate 1
- Bulls Lodge Farm 2England and Wales, Storage with solar or windMarked as Gate 1
- Enderby Farm 2England and Wales, Storage with solar or windMarked as Gate 1
- Marston Farm 2England and Wales, Storage with solar or windMarked as Gate 1
- Sundon Farm 2England and Wales, Storage with solar or windMarked as Gate 1
- Bulls Lodge FarmEngland and Wales, Storage with solar or windMarked as Gate 1
- Enderby FarmEngland and Wales, Storage with solar or windMarked as Gate 1
- Patford Bridge Farm 2England and Wales, Storage with solar or windMarked as Gate 1
- Ryhall FarmEngland and Wales, Storage with solar or windMarked as Gate 1
- Sundon FarmEngland and Wales, Storage with solar or windMarked as Gate 1
- Yaxley FarmEngland and Wales, Storage with solar or windMarked as Gate 1
- Bulls Lodge FarmEngland and Wales, Storage with solar or windConnection date moved from 30 Mar 2033 to 30 Apr 2033 (+1 month)+1 mo
- Bulls Lodge FarmEngland and Wales, Storage with solar or windConnection point changed from Bulls Lodge 400kV Substation to Braintree 400kV Substation
- Bulls Lodge FarmEngland and Wales, Storage with solar or windConnection date moved from 30 Apr 2033 to 30 Mar 2033 (−1 month)−1 mo
- Bulls Lodge Farm 2England and Wales, Storage with solar or windConnection point changed from Bulls Lodge 400kV Substation to Braintree 400kV Substation
- Enderby FarmEngland and Wales, Storage with solar or windConnection point changed from Enderby 400kV Substation to Earl Shilton 400kV Substation
- Sundon FarmEngland and Wales, Storage with solar or windConnection point changed from Sundon 400kV Substation to Dunstable 400kV Substation
- Sundon FarmEngland and Wales, Storage with solar or windConnection date moved from 30 Apr 2033 to 29 Oct 2032 (−6 months)−6 mo
- Sundon Farm 2England and Wales, Storage with solar or windConnection point changed from Sundon 400kV Substation to Dunstable 400kV Substation
- Pelham Farm 2England and Wales, Storage with solar or windAdded to the registerNew
- Pelham FarmEngland and Wales, Storage with solar or windLeft the register (700 MW from 31 Oct 2032)700 MW
- Patford Bridge Farm 2England and Wales, Storage with solar or windConnection point changed from Patford Bridge 400kV Substation to New Patford Bridge 400kV Substation
- Enderby Farm 2England and Wales, Storage with solar or windAdded to the registerNew
- Patford Bridge Farm 2England and Wales, Storage with solar or windAdded to the registerNew
- Bulls Lodge FarmEngland and Wales, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose