Bulls Lodge Farm
548 UK INVESTMENT HOLDINGS LIMITED at Braintree 400kV Substation
- Connection date
- Left 13 Nov 2026
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002676
- In the register since
- July 2023
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 13 Nov 2026 registerLeft the register (200 MW from 30 Apr 2033)
- 10 Oct 2026 registerListed again
- 22 May 2026 registerNot in this register
- 28 Nov 2025 registerMarked as Gate 1
- 24 Dec 2024 registerConnection date moved from 30 Mar 2033 to 30 Apr 2033 (+1 month)
- 28 Jun 2024 registerConnection point changed from Bulls Lodge 400kV Substation to Braintree 400kV Substation
- 28 Jun 2024 registerConnection date moved from 30 Apr 2033 to 30 Mar 2033 (−1 month)
- 28 Jul 2023 registerAdded to the register
Also at Braintree 400kV Substation
Substation view3 other projects, 1.1 GW still to connect at this substation in total.