Berwick Bank B Limited
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Berwick Bank Offshore Wind Farm B | Branxton 400kV Substation | Offshore wind | 1,380 | 31 Oct 2029 | Not stated | Scoping |
Recent changes
- Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windConnection point changed from Branxton 400/132KV Substation to Branxton 400kV Substation
- Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windConnection point changed from Berwick Bank B 275/66kV Offshore Substation to Branxton 400/132KV Substation
- Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windStage 1: Capacity changed from 250 MW to 1,150 MW
- Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windStage 2: Capacity changed from 900 MW to 230 MW
- Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windStage 2: Connection date moved from 31 Oct 2029 to 30 Jun 2031 (+20 months)+20 mo
- Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windStage 1: Connection date moved from 30 Oct 2029 to 31 Oct 2029 (1 day later)
- Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windStage 2: Connection date moved from 30 Oct 2029 to 31 Oct 2029 (1 day later)
- Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windStage 1: Connection date moved from 27 Nov 2027 to 30 Oct 2029 (+23 months)+23 mo
- Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windStage 2: Connection date moved from 30 Dec 2027 to 30 Oct 2029 (+22 months)+22 mo
- Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windRenamed from Firth of Forth Offshore Wind Farm 2B
- Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windCustomer changed from SEAGREEN WIND ENERGY LIMITED to Berwick Bank B Limited
- Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windConnection point changed from Branxton 400kV Substation to Berwick Bank B 275/66kV Offshore Substation
- Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windStage 1: Capacity changed from 700 MW to 250 MW
- Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windStage 1: Connection date moved from 27 Nov 2026 to 27 Nov 2027 (+12 months)+12 mo
- Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windStage 2: Capacity changed from 450 MW to 900 MW
- Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windStage 2: Connection date moved from 26 Nov 2027 to 30 Dec 2027 (+1 month)+1 mo
- Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windSubstation name updated in the register (from Branxton 400kV to Branxton 400kV Substation)
- Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windRestructured from 1 stage (700 MW from 1 Apr 2024) to 2 stages (700 MW from 27 Nov 2026, 450 MW from 26 Nov 2027). First connection date +32 months+32 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose