Berwick Bank Offshore Wind Farm B
- Connection date
- 31 Oct 2029
- Gate
- Not stated
- Status
- Scoping
- Technology
- Offshore wind
- Total capacity
- 1,380 MW
- Connected now
- 0 MW
- Still to connect
- 1,380 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-002628
- In the register since
- January 2021 or earlier
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 1,150 | 1,150 | 31 Oct 2029 | Not stated | Scoping |
| 2 | 0 | 230 | 1,380 | 30 Jun 2031 | Not stated | Scoping |
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 19 Dec 2025 registerConnection point changed from Branxton 400/132KV Substation to Branxton 400kV Substation
- 27 Jun 2025 registerConnection point changed from Berwick Bank B 275/66kV Offshore Substation to Branxton 400/132KV Substation
- 27 Jun 2025 registerStage 1: Capacity changed from 250 MW to 1,150 MW
- 27 Jun 2025 registerStage 2: Capacity changed from 900 MW to 230 MW
- 27 Jun 2025 registerStage 2: Connection date moved from 31 Oct 2029 to 30 Jun 2031 (+20 months)
- 28 Feb 2025 registerStage 1: Connection date moved from 30 Oct 2029 to 31 Oct 2029 (1 day later)
- 28 Feb 2025 registerStage 2: Connection date moved from 30 Oct 2029 to 31 Oct 2029 (1 day later)
- 27 Aug 2024 registerStage 1: Connection date moved from 27 Nov 2027 to 30 Oct 2029 (+23 months)
- 27 Aug 2024 registerStage 2: Connection date moved from 30 Dec 2027 to 30 Oct 2029 (+22 months)
- 31 Mar 2023 registerRenamed from Firth of Forth Offshore Wind Farm 2B
- 31 Mar 2023 registerCustomer changed from SEAGREEN WIND ENERGY LIMITED to Berwick Bank B Limited
- 31 Mar 2023 registerConnection point changed from Branxton 400kV Substation to Berwick Bank B 275/66kV Offshore Substation
- 31 Mar 2023 registerStage 1: Capacity changed from 700 MW to 250 MW
- 31 Mar 2023 registerStage 1: Connection date moved from 27 Nov 2026 to 27 Nov 2027 (+12 months)
- 31 Mar 2023 registerStage 2: Capacity changed from 450 MW to 900 MW
- 31 Mar 2023 registerStage 2: Connection date moved from 26 Nov 2027 to 30 Dec 2027 (+1 month)
- 23 Dec 2022 registerSubstation name updated in the register (from Branxton 400kV to Branxton 400kV Substation)
- 30 Mar 2021 registerRestructured from 1 stage (700 MW from 1 Apr 2024) to 2 stages (700 MW from 27 Nov 2026, 450 MW from 26 Nov 2027). First connection date +32 months
Also at Branxton 400kV Substation
Substation view2 other projects, 3.5 GW still to connect at this substation in total. 1.9 GW is due to connect here before this project’s connection date of 31 Oct 2029.