HEADWIND DEVELOPMENT SERVICES LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Beinn Ghlas | Taynuilt 132/33kV GSP Substation | Onshore wind | 35.0 | 28 Mar 2031 −43 mo | Gate 2 | Consents Approved |
| Novar 2 Wind Farm | Alness GSP | Onshore wind | 43.2 | 31 Oct 2032 | Gate 1 | Scoping |
| Causeymire 2 Wind Farm | Mybster 4 132/33kV GSP Substation | Onshore wind | 39.6 | 31 Oct 2034 | Gate 1 | Scoping |
Recent changes
- Beinn GhlasNorth Scotland, Onshore windConnection point changed from Taynuilt GSP to Taynuilt 132/33kV GSP Substation
- Beinn GhlasNorth Scotland, Onshore windCapacity changed from 57.6 MW to 35 MW
- Beinn GhlasNorth Scotland, Onshore windConnection date moved from 31 Oct 2034 to 28 Mar 2031 (−43 months)−43 mo
- Beinn GhlasNorth Scotland, Onshore windStatus changed from Awaiting Consents to Consents Approved
- Beinn GhlasNorth Scotland, Onshore windGiven a Gate 2 connection offerGate 2
- Causeymire 2 Wind FarmNorth Scotland, Onshore windSubstation name updated in the register (from Mybster 4 GSP to Mybster 4 132/33kV GSP Substation)
- Causeymire 2 Wind FarmNorth Scotland, Onshore windMarked as Gate 1
- Novar 2 Wind FarmNorth Scotland, Onshore windMarked as Gate 1
- Causeymire 2 Wind FarmNorth Scotland, Onshore windAdded to the registerNew
- Novar 2 Wind FarmNorth Scotland, Onshore windAdded to the registerNew
- Beinn GhlasNorth Scotland, Onshore windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?