- Connection date
- 28 Mar 2031 −43 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Onshore wind
- Total capacity
- 35 MW
- Connected now
- 0 MW
- Still to connect
- 35 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-004073
- In the register since
- October 2024
Read our analysis: Gate 2 in the transmission queue
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 10 Nov 2026 registerConnection point changed from Taynuilt GSP to Taynuilt 132/33kV GSP Substation
- 10 Nov 2026 registerCapacity changed from 57.6 MW to 35 MW
- 10 Nov 2026 registerConnection date moved from 31 Oct 2034 to 28 Mar 2031 (−43 months)
- 10 Nov 2026 registerStatus changed from Awaiting Consents to Consents Approved
- 10 Nov 2026 registerGiven a Gate 2 connection offer
- 29 Oct 2024 registerAdded to the register
Also at Taynuilt 132/33kV GSP Substation
Substation viewNo other projects in the register at this connection point.