Pathfinder Clean Energy (PACE)
Customer named in the DNOs’ registers
In UKPN’s November 2026 edition
Capacity by DNO
| DNO | Edition | Sites | Capacity | Connected | Accepted to connect |
|---|---|---|---|---|---|
| UKPN | November 2026 edition | 4 | 142 MW | 15 MW | 127 MW |
Capacity by technology
| Technology | Sites | Capacity | Connected | Accepted to connect |
|---|---|---|---|---|
| Solar | 4 | 142 MW | 15 MW | 127 MW |
Each site is grouped by its first energy source, as the register names it.
Sites
Each site under this name in the DNOs’ latest editions, the largest first.
Site, company and substation names are shown as they appear in the registers, including capitalisation.
| Site | DNO | Grid supply point | Technology | Status | MW |
|---|---|---|---|---|---|
| (ANM) Land Off Twinwood Road | UKPN | Eaton Socon | Solar | Accepted to connect | 69 |
| (ANM) Ashwell Road | UKPN | Wymondley | Solar | Accepted to connect | 40 |
| (ANM) Bunwell Road | UKPN | Norwich | Solar | Accepted to connect | 18 |
| Land West Of Spixworth Road | UKPN | Norwich | Solar | Connected | 15 |
Grid supply points
Each grid supply point its sites are at, with the capacity of its own sites there.
| Grid supply point | DNO | Sites | Connected | Accepted to connect |
|---|---|---|---|---|
| Eaton Socon | UKPN | 1 | – | 69 MW |
| Wymondley | UKPN | 1 | – | 40 MW |
| Norwich | UKPN | 2 | 15 MW | 18 MW |
What changed recently
Changes to its sites found in both editions of each pair, newest first.
UKPN, October 2026 edition to November 2026 edition, for this customer’s sites: 4 sites matched. Every October site and every November site had a match in the other edition.
- (ANM) Ashwell RoadUKPN, November 2026 editionTarget energisation date moved from 31 Dec 2024 to 30 Mar 2026 (15 months later)
- (ANM) Bunwell RoadUKPN, November 2026 editionTarget energisation date moved from 31 Oct 2030 to 31 Dec 2031 (14 months later)
- (ANM) Land Off Twinwood RoadUKPN, November 2026 editionTarget energisation date moved from 31 Oct 2028 to 27 Oct 2037 (108 months later)
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?