FAWLEY GSP
Grid supply point in Southern England (SEPD)
SSEN Embedded Capacity Register, November 2026 edition
Capacity by technology
| Technology | Sites | Capacity | Connected | Accepted to connect |
|---|---|---|---|---|
| Other or not stated | 4 | 380 MW | 377 MW | 3 MW |
| Solar | 17 | 181 MW | 87 MW | 94 MW |
| Storage | 1 | 99 MW | – | 99 MW |
| Hydro and marine | 2 | 24.6 MW | 4.8 MW | 19.8 MW |
| Bioenergy and waste | 3 | 8.1 MW | 3.5 MW | 4.6 MW |
Storage capacity in MWh: not published by SSEN.
Each site is grouped by its first energy source, as the register names it.
How busy is each primary substation?
Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.
Site, company and substation names are shown as they appear in the registers, including capitalisation.
| Primary substation | Bulk supply point | Sites | Connected | Accepted to connect | |||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| COWES & WOOTTON COMMON | 2 | – | 48.3 MW | ||||||||||||||||||||||||||
2 sites, 48.3 MW: 48.3 MW accepted to connect
| |||||||||||||||||||||||||||||
| COWES & WOOTTON COMMON | 3 | 33.3 MW | 7.1 MW | ||||||||||||||||||||||||||
3 sites, 40.4 MW: 33.3 MW connected, 7.1 MW accepted to connect
| |||||||||||||||||||||||||||||
| COWES & WOOTTON COMMON | 1 | 8.7 MW | – | ||||||||||||||||||||||||||
1 site, 8.7 MW: 8.7 MW connected
| |||||||||||||||||||||||||||||
| COWES & WOOTTON COMMON | 2 | 7.7 MW | – | ||||||||||||||||||||||||||
2 sites, 7.7 MW: 7.7 MW connected
| |||||||||||||||||||||||||||||
| COWES & WOOTTON COMMON | 1 | 6.7 MW | – | ||||||||||||||||||||||||||
1 site, 6.7 MW: 6.7 MW connected
| |||||||||||||||||||||||||||||
| COWES & WOOTTON COMMON | 1 | 6.5 MW | – | ||||||||||||||||||||||||||
1 site, 6.5 MW: 6.5 MW connected
| |||||||||||||||||||||||||||||
| COWES & WOOTTON COMMON | 2 | 1.4 MW | 5 MW | ||||||||||||||||||||||||||
2 sites, 6.4 MW: 1.4 MW connected, 5 MW accepted to connect
| |||||||||||||||||||||||||||||
| COWES & WOOTTON COMMON | 1 | 4.8 MW | – | ||||||||||||||||||||||||||
1 site, 4.8 MW: 4.8 MW connected
| |||||||||||||||||||||||||||||
| COWES & WOOTTON COMMON | 1 | 4.8 MW | – | ||||||||||||||||||||||||||
1 site, 4.8 MW: 4.8 MW connected
| |||||||||||||||||||||||||||||
| COWES & WOOTTON COMMON | 1 | 4.8 MW | – | ||||||||||||||||||||||||||
1 site, 4.8 MW: 4.8 MW connected
| |||||||||||||||||||||||||||||
| COWES & WOOTTON COMMON | 2 | 3.5 MW | – | ||||||||||||||||||||||||||
2 sites, 3.5 MW: 3.5 MW connected
| |||||||||||||||||||||||||||||
| COWES & WOOTTON COMMON | 1 | 3.3 MW | – | ||||||||||||||||||||||||||
1 site, 3.3 MW: 3.3 MW connected
| |||||||||||||||||||||||||||||
| COWES & WOOTTON COMMON | 1 | 2.7 MW | – | ||||||||||||||||||||||||||
1 site, 2.7 MW: 2.7 MW connected
| |||||||||||||||||||||||||||||
| COWES & WOOTTON COMMON | 2 | – | 60 MW | ||||||||||||||||||||||||||
2 sites, 60 MW: 60 MW accepted to connect
| |||||||||||||||||||||||||||||
| LANGLEY | 2 | 7.6 MW | – | ||||||||||||||||||||||||||
2 sites, 7.6 MW: 7.6 MW connected
| |||||||||||||||||||||||||||||
| Not stated | 4 | 377 MW | 99 MW | ||||||||||||||||||||||||||
4 sites, 476 MW: 377 MW connected, 99 MW accepted to connect
| |||||||||||||||||||||||||||||
Not found among the sites of 1 MW and over in SSEN’s November 2026 edition
1 site last found at this grid supply point was not found among this edition’s sites of 1 MW and over by its MPAN, grid reference or name and postcode. QueueWatch keeps its page for six months and does not say whether it has left the register.
- LAND AT IPERS BRIDGE last found in the September 2026 edition
What changed recently
Changes to sites here found in both editions of each pair, newest first.
October 2026 edition to November 2026 edition: 27 sites matched. Every October site and every November site at this grid supply point had a match in the other edition.
- WERRAR FARMAugust 2026 editionExport capacity changed from 45 MW to 9.474 MW
- WERRAR FARMJuly 2026 editionExport capacity changed from 9.474 MW to 45 MW
- WERRAR FARMMay 2026 editionExport capacity changed from 45 MW to 9.474 MW
- WERRAR FARMApril 2026 editionExport capacity changed from 9.474 MW to 45 MW
- WERRAR FARMFebruary 2026 editionExport capacity changed from 35 MW to 9.474 MW
- LANE END ENERGY CENTREJuly 2025 editionTechnology stated as Bioenergy and waste (not stated in the June 2025 edition)
- BNRG IOW LTDApril 2025 editionTechnology stated as Solar (not stated in the March 2025 edition)
- IMP EXP SUPPLYApril 2025 editionTechnology stated as Bioenergy and waste (not stated in the March 2025 edition)
- Site not namedApril 2025 editionTechnology stated as Solar (not stated in the March 2025 edition)
- LAND AT IPERS BRIDGEMay 2024 editionCapacity changed from 150 MW to 120 MW
- LAND AT IPERS BRIDGEMay 2024 editionTechnology changed from Storage to Other
- FAIRLEE FARM PV GENERATIONNovember 2023 editionCapacity stated as 6.546 MW (not stated in the October 2023 edition)
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?
How power reaches a site
A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.