Progress Power Station
- Connection date
- 28 Jun 2024
- Gate
- Not stated
- Status
- Under Construction/Commissioning
- Planning consent
- Granted 23 Jul 2015
Progress Power Station (EN010060) · Source: Planning Inspectorate - Technology
- Gas (OCGT)
- Total capacity
- 299 MW
- Connected now
- 0 MW
- Still to connect
- 299 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000274
- In the register since
- January 2021 or earlier
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 30 May 2023 registerStatus changed from Consents Approved to Under Construction/Commissioning
- 23 Dec 2022 registerSubstation name updated in the register (from Yaxley 400kV to Yaxley 400kV Substation)
- 28 Jan 2022 registerConnection date moved from 1 Aug 2022 to 28 Jun 2024 (+23 months)
Also at Yaxley 400kV Substation
Substation view3 other projects, 998 MW still to connect at this substation in total.