Yaxley GEC (Ethos Green)
- Connection date
- 31 Oct 2031
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Storage + Solar
- Total capacity
- 450 MW
- Connected now
- 0 MW
- Still to connect
- 450 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003935
- In the register since
- July 2023
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 7 Aug 2026 registerTechnology changed from Demand, Storage, Solar, Reactive compensation to Storage, Solar
- 31 Oct 2023 registerRenamed from Yaxley GEC
- 28 Jul 2023 registerAdded to the register
Also at Yaxley 400kV Substation
Substation view3 other projects, 998 MW still to connect at this substation in total. 548 MW is due to connect here before this project’s connection date of 31 Oct 2031.