Millbrook Power
- Connection date
- 28 Jun 2024
- Gate
- Not stated
- Status
- Under Construction/Commissioning
- Planning consent
- Granted 13 Mar 2019
Millbrook Power (EN010068) · Source: Planning Inspectorate - Technology
- Gas (OCGT)
- Total capacity
- 299 MW
- Connected now
- 0 MW
- Still to connect
- 299 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000373
- In the register since
- January 2021 or earlier
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 30 May 2023 registerStatus changed from Consents Approved to Under Construction/Commissioning
- 28 Jan 2022 registerConnection date moved from 15 Jul 2022 to 28 Jun 2024 (+23 months)
- 28 Jan 2022 registerStatus changed from Scoping to Consents Approved
- 31 Dec 2021 registerConnection point changed from Millbrook 400kV to Marston Vale 400kV substation
Also at Marston Vale 400kV Substation
Substation view1 other project, 539 MW still to connect at this substation in total.