Lightsource Marston Vale 240MW PV+BESS
Lightsource Renewable UK Development Limited at Marston Vale 400kV Substation
- Connection date
- 31 Oct 2034
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 240 MW
- Connected now
- 0 MW
- Still to connect
- 240 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003981
- In the register since
- December 2023
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 16 Oct 2026 registerConnection date moved from 30 Oct 2034 to 31 Oct 2034 (1 day later)
- 10 Oct 2026 registerConnection date moved from 31 Oct 2034 to 30 Oct 2034 (1 day earlier)
- 13 Mar 2026 registerMarked as Gate 1
- 24 Dec 2024 registerConnection date moved from 30 Oct 2036 to 31 Oct 2034 (−24 months)
- 29 Dec 2023 registerAdded to the register
Also at Marston Vale 400kV Substation
Substation view1 other project, 539 MW still to connect at this substation in total. 299 MW is due to connect here before this project’s connection date of 31 Oct 2034.