Exeter Main Tertiary
- Connection date
- 1 May 2024
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Thermal
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000452
- In the register since
- January 2021 or earlier
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 10 Nov 2026 registerMarked as Gate 1
- 23 Dec 2022 registerConnection point changed from Exeter Main 400kV to Exeter 400kV Substation
- 29 Oct 2021 registerCustomer changed from EXETER MAIN SOLAR LIMITED to EXETER MAIN BATTERY LIMITED
Also at Exeter 400kV Substation
Substation view3 other projects, 1.2 GW still to connect at this substation in total.