Exeter Main
- Connection date
- 28 Oct 2033
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002082
- In the register since
- June 2023
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 9 Dec 2025 registerMarked as Gate 1
- 29 Jul 2025 registerCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
- 24 Dec 2024 registerConnection date moved from 24 Nov 2031 to 28 Oct 2033 (+23 months)
- 30 Jun 2023 registerAdded to the register
Also at Exeter 400kV Substation
Substation view3 other projects, 1.2 GW still to connect at this substation in total. 397 MW is due to connect here before this project’s connection date of 28 Oct 2033.