Braintree (Tertiary)
- Connection date
- 30 Oct 2026
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage + Solar
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001043
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 27 Jun 2025 registerStatus changed from Awaiting Consents to Consents Approved
- 24 Dec 2024 registerTechnology changed from Solar to Storage, Solar
- 30 Jul 2024 registerConnection date moved from 30 Jul 2025 to 30 Oct 2026 (+15 months)
- 30 May 2023 registerStatus changed from Scoping to Awaiting Consents
- 28 Feb 2023 registerConnection point changed from Braintree GSP to Braintree 400kV Substation
- 30 Mar 2022 registerSubstation name updated in the register (from Braintree to Braintree GSP)
- 25 Feb 2022 registerConnection date moved from 30 Oct 2025 to 30 Jul 2025 (−3 months)
- 28 Jan 2022 registerConnection date moved from 30 Jul 2025 to 30 Oct 2025 (+3 months)
Also at Braintree 400kV Substation
Substation view2 other projects, 1.1 GW still to connect at this substation in total.