- Connection date
- 31 Oct 2034
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003406
- In the register since
- October 2023
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 18 Sep 2026 registerMarked as Gate 1
- 27 Sep 2024 registerConnection date moved from 31 Oct 2032 to 31 Oct 2034 (+24 months)
- 26 Apr 2024 registerCustomer changed from ORRÖN ENERGY DEVELOPMENT LIMITED to Braintree 10 Renewables Limited
- 31 Oct 2023 registerAdded to the register
Also at Braintree 400kV Substation
Substation view2 other projects, 1.1 GW still to connect at this substation in total. 107 MW is due to connect here before this project’s connection date of 31 Oct 2034.