Lambeeth 240MW
- Connection date
- Left 13 Nov 2026
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 240 MW
- Connected now
- 0 MW
- Still to connect
- 240 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004361
- In the register since
- October 2024
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Read our analysis: The battery queue and CMP470’s commitment fee
Read our analysis: Delays and exits in the transmission queue since 2021
Read our analysis: Do projects connect on time?
Change history
Every change to this project across 154 registers from 29 Jan 2021 to 16 Nov 2026.
- 13 Nov 2026 registerLeft the register (240 MW from 31 Dec 2037)
- 24 Sep 2026 registerMarked as Gate 1
- 29 Oct 2024 registerAdded to the register
Also at Pembroke 400kV Substation
Substation view6 other projects, 1.2 GW still to connect at this substation in total.
- Llŷr Floating WindLlŷr Floating Wind Limited, Offshore wind, Not statedOct 2028200 MW
- Pembroke BESS and Solar StationRenesola Hercules Energy 1 Limited, Storage with solar or wind, Not statedOct 202899.9 MW
- Pembroke BESSRWE Generation UK Plc, Storage, Gate 2Mar 2029350 MW
- Llywelyn Floating Offshore Wind FarmRenantis UK Limited, Offshore wind, Gate 1Mar 2029300 MW
- Valorous Offshore Wind FarmBlue Gem Wind Limited, Offshore wind, Not statedOct 2031300 MW
- Pembroke Power StationRWE Generation UK Plc, Other, Not statedConnected2.2 GW