PIPPLEPEN FARM SOLAR PV

DNO CONSULTING LTD at AXMINSTER

SSEN Embedded Capacity Register, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
5 Mar 2029
Status
Accepted to connect
Planning consent
Granted 24 Jan 2023
Somerset, reference 21/00701/FUL · Source: REPD
Customer
DNO CONSULTING LTD
Site name
PIPPLEPEN FARM SOLAR PV
Address
PIPPLEPEN FARM SOLAR PV, LANDS AT PIPPLEPEN FARM, BEAMINSTER, DORSET, DT8 3HS
Grid reference
Easting 347256, northing 106836
Licence area
Southern England (SEPD)
Grid supply point
AXMINSTER
Bulk supply point
Not stated
Primary substation
Not stated
Connection voltage
132 kV
Technology group
Solar
Energy source 1
SOLAR, PHOTOVOLTAIC: 32.6 MW registered
Registered capacity
32.6 MW
Change to maximum export capacity
30 MW
Change to maximum import capacity
0.09 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
29 Feb 2024
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
March 2024 edition

Change history

Tracked since the March 2024 edition, across 33 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2025 edition
    Target energisation date stated as 5 Mar 2029 (not stated in the October 2025 edition)

Also at AXMINSTER

GSP view

24 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 408 MW: 126 MW connected, 282 MW accepted to connect.

See all 24

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.