HIGHER STOCKBRIDGE FARM PV
MARTIFER SOLAR UK LTD at AXMINSTER
SSEN Embedded Capacity Register, November 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 30 Oct 2026
- Status
- Accepted to connect
- Planning consent
- Granted 8 Dec 2021
Dorset, reference WD/D/19/003181 · Source: REPD - Contract for Difference
- Allocation Round 4
- Customer
- MARTIFER SOLAR UK LTD
- Site name
- HIGHER STOCKBRIDGE FARM PV
- Address
- HIGHER STOCKBRIDGE FARM PV, LONGBURTON, SHERBORNE, DORSET, DT9 6EP
- Grid reference
- Easting 363877, northing 111078
- Licence area
- Southern England (SEPD)
- Grid supply point
- AXMINSTER
- Bulk supply point
- Not stated
- Primary substation
- Not stated
- Connection voltage
- 132 kV
- Technology group
- Solar
- Energy source 1
- SOLAR, PHOTOVOLTAIC: 35 MW registered
- Registered capacity
- 35 MW
- Change to maximum export capacity
- 35 MW
- Change to maximum import capacity
- 0.447 MW
- Flexible connection
- Not stated
- In a connection queue
- Not published by SSEN
- Date accepted
- 25 Jan 2022
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SSEN
- Transmission reinforcement reference
- Not published by SSEN
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 10 Feb 2026
- Tracked since
- August 2023 edition
Change history
Tracked since the August 2023 edition, across 40 editions.
Changes to the details QueueWatch tracks, newest first.
- November 2025 editionTarget energisation date stated as 30 Oct 2026 (not stated in the October 2025 edition)
Also at AXMINSTER
GSP view24 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 408 MW: 126 MW connected, 282 MW accepted to connect.
- CONRAD (YEOVIL) LIMITEDCONRAD (YEOVIL) LIMITED, Gas and other fossil, YEOVIL primaryConnected15.21 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?
Planning consent
The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.
How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.
Contract for Difference
The Contracts for Difference allocation round for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition. QueueWatch matched the site to that record.
How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.