CLIFTON FARM

CLIFTON SOLAR LTD at AXMINSTER

SSEN Embedded Capacity Register, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Date connected
2 Oct 2025
Status
Connected
Planning consent
Granted 20 May 2021
Dorset, reference WD/D/20/001057 · Source: REPD
Contract for Difference
Allocation Round 4
Customer
CLIFTON SOLAR LTD
Site name
CLIFTON FARM
Address
YEOVIL, SOMERSET, BA22 9UZ
Grid reference
Easting 357576, northing 113731
Licence area
Southern England (SEPD)
Grid supply point
AXMINSTER
Bulk supply point
YEOVIL
Primary substation
WEST HENDFORD
Connection voltage
132 kV
Technology group
Solar
Energy source 1
SOLAR, PHOTOVOLTAIC: 35 MW registered
Registered capacity
35 MW
Maximum export capacity
35 MW
Maximum import capacity
0.404 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
Not stated
Target energisation date
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
2000060717815
Import MPAN
2000060717806
Last updated
12 Feb 2026
Tracked since
October 2025 edition

Change history

Tracked since the October 2025 edition, across 14 editions.

Changes to the details QueueWatch tracks, newest first.

No change to any detail QueueWatch tracks.

Also at AXMINSTER

GSP view

24 other sites at this grid supply point in the November 2026 edition, 2 of them at WEST HENDFORD, the same primary substation. In all, the sites here total 408 MW: 126 MW connected, 282 MW accepted to connect.

See all 24

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.

Contract for Difference

The Contracts for Difference allocation round for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition. QueueWatch matched the site to that record.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.